The North Dakota Public Service Commission approved a final route for the state’s largest transmission line project in decades.  Minnkota Power Cooperative will construct the 250-mile line from Center, North Dakota, to Grand Forks.  The project is estimated to cost approximately $312 million.  Construction is expected to be completed by the end of 2013.  Click here for the full story.